Momentum Build (NW) – Retail Demolition and Electrical Works, Liverpool ONE

ClientMomentum Build (NW)
LocationLiverpool ONE
ServicesIsolation and safe removal of existing electrical systems.
Installation of temporary electrical supplies.
Provision of electrical feeds.
Date2025

Overview

DATO Services was appointed by Momentum Build (NW) to carry out electrical works during the demolition of a former Harvey Nichols retail unit within Liverpool ONE. The scope included making the existing installation safe, providing site temporary supplies for demolition activities, and ensuring the unit was returned to a bare shell — ready for the incoming retailer’s new fit-out.


Challenges

The project began with just five days’ notice, requiring rapid mobilisation and coordination with multiple contractors on site. As demolition progressed, additional works were requested to accommodate changing requirements and maintain site safety and operational efficiency.


The Solution

DATO Services successfully completed the project within two weeks, meeting all safety requirements and delivering a safe, blank canvas for the next phase of retail redevelopment. Our responsive approach ensured that works continued without delay despite the short notice period and dynamic site conditions.

Key services provided:

  • Isolation and safe removal of existing electrical systems.
  • Installation of temporary electrical supplies to support demolition tools and lighting.
  • Provision of electrical feeds for specialist cutting and site equipment.
  • Ongoing coordination with the demolition team to adapt works as the site evolved.

At DATO Services, we’re committed to delivering a reliable, safe, and quality-assured service on every project, every time. Our partnerships and accreditations reflect our dedication to maintaining the highest standards across all our work.